Electra reports progress on cobalt refinery project

September 28, 2022
By Canadian Manufacturing

Presented by:
CMO

Electra’s refinery will produce enough cobalt sulfate to supply up to 1.5 million electric vehicles per year. (CNW Group/Electra Battery Materials Corporation)

TORONTO — On Sep. 28, Electra Battery Materials Corporation provided an update on the commissioning of its cobalt refinery located north of Toronto, confirming that it remains on track to meet project timelines, including the launch of a black mass recycling demonstration, and capital cost guidance announced with its Q2 2022 reporting.

“Electra continues to build momentum,” said Trent Mell, CEO of Electra Battery Materials. “On the heels of our commercial agreement with LG Energy Solution announced last week, we are excited by the continued progress at our refinery and the prospects of our upcoming black mass recycling demonstration plant. Building upon successful metallurgical testing and engineering work, and the receipt and installation of key pieces of equipment, we anticipate launching our battery recycling demonstration plant at the Ontario refinery site this fall.”

Mr. Mell added, “The plant demonstration, which will be conducted in concert with ongoing commissioning efforts at the refinery, is expected to produce five marketable products. Revenue generated from black mass recycling activities will be accretive to results expected from the sale of cobalt sulfate that is anticipated beginning in spring 2023 when the refinery is commissioned.”

Refinery Commissioning Highlights
Through September 28, 2022, Electra’s progress on the refinery commissioning project can be measured by a number of key developments, including:

  • Completed 85 percent of testing of existing brownfield equipment for recommissioning.
  • Completed 85 percent of all procurement.
  • Completed 90 percent of detailed engineering.
  • Completed 75 percent of the erection of the solvent extraction building, and major solvent extraction equipment will start to be placed by the end of October.
  • Foundations and structural steel work continue for the crystallizer plant, and key processing equipment, including falling film evaporator and crystallizer vessels, are scheduled to be installed in early November.
  • Other equipment already at site to support the buildout of the crystallizer plant process include two steam package boilers, a crystallizer plant condenser, condensate and cobalt sulphate feed tanks, and a crystallizer centrifuge.
  • The owners’ team is now at 25 personnel, consisting of trades people, engineers, operators, lab technicians, and office support staff.

Black Mass Recycling Demonstration
Electra has completed process development and engineering on recycling black mass material, a byproduct generated by the end-of-life EV battery recycling and other recycled lithium-based battery sources.

Electra is retrofitting its existing refinery to accommodate its black mass process and plans to conduct large scale bulk runs to establish the process parameters, generate data for further optimization and validate the recoveries and quality of various marketable products.

Electra will use a hydrometallurgical process to the treat black mass. This process has a low carbon footprint and produces stable non-acid generating tailings, thereby reducing environmental impacts while meeting or exceeding water discharge effluent criteria as stipulated by both federal and provincial regulations.